LSAT 103 – Section 1 – Question 23
You need a full course to see this video. Enroll now and get started in less than a minute.
Target time: 2:25
This is question data from the 7Sage LSAT Scorer. You can score your LSATs, track your results, and analyze your performance with pretty charts and vital statistics - all with a Free Account ← sign up in less than 10 seconds
Question QuickView |
Type | Tags | Answer Choices |
Curve | Question Difficulty |
Psg/Game/S Difficulty |
Explanation |
---|---|---|---|---|---|---|---|
PT103 S1 Q23 |
+LR
+Exp
| Resolve reconcile or explain +RRE | A
5%
160
B
5%
159
C
7%
160
D
46%
167
E
37%
164
|
155 167 180 |
+Hardest | 147.884 +SubsectionMedium |
Kevin’s explanation
You need a full course to see this video. Enroll now and get started in less than a minute.
"Surprising" Phenomenon
Why are cost overruns more common in the fixed-profit kind of “cost-plus” contract than in the fixed-percentage kind of “cost-plus” contract, even though under the fixed-percentage kind higher costs would lead to higher profits for the contractor?
Objective
The correct answer should tell us about a difference between the fixed-profit and fixed-percentage kinds of “cost-plus” contract that would lead to a higher likelihood of cost overruns for the fixed-profit kind.
A
Clients are much less likely to agree to a fixed-profit type of cost-plus contract when it is understood that under certain conditions the project will be scuttled than they are when there is no such understanding.
This tells us about likelihood of accepting a fixed-profit contract when there are conditions that would lead to the end of the project. But this doesn’t impact the costs incurred on a project or why those costs more commonly go over expected costs for fixed-profits contracts.
B
On long-term contracts, cost projections take future inflation into account, but since the figures used are provided by the government, they are usually underestimates.
This doesn’t differentiate between fixed-profit and fixed-percentage contracts, so it’s not going to explain why cost overruns are more common for fixed-profit contracts.
C
On any sizable construction project, the contractor bills the client monthly or quarterly, so any tendency for original cost estimates to be exceeded can be detected early.
This doesn’t differentiate between fixed-profit and fixed-percentage contracts, so it’s not going to explain why cost overruns are more common for fixed-profit contracts.
D
Clients billed under a cost-plus contract are free to review individual billings in order to uncover wasteful expenditures, but they do so only when the contractor’s profit varies with cost.
If clients review for wasteful expenditures only when profit varies with cost, that means they don’t review for wasteful expenditures on fixed-profit contracts (where profit doesn’t vary with cost). This could be why cost overruns are more common for this kind of contract.
E
The practice of submitting deliberately exaggerated cost estimates is most common in the case of fixed-profit contracts, because it makes the profit, as a percentage of estimated cost, appear modest.
Cost overruns involve the excess cost over the estimated cost. If fixed-profit contracts more often involve exaggerated estimates, that should lead us to expect fewer cost overruns for these contracts, since the initial estimate would be higher than the actual expected costs.
Take PrepTest
Review Results
LSAT PrepTest 103 Explanations
Section 1 - Logical Reasoning
- Question 01
- Question 02
- Question 03
- Question 04
- Question 05
- Question 06
- Question 07
- Question 08
- Question 09
- Question 10
- Question 11
- Question 12
- Question 13
- Question 14
- Question 15
- Question 16
- Question 17
- Question 18
- Question 19
- Question 20
- Question 21
- Question 22
- Question 23
- Question 24
- Question 25
- Question 26
Section 2 - Logical Reasoning
- Question 01
- Question 02
- Question 03
- Question 04
- Question 05
- Question 06
- Question 07
- Question 08
- Question 09
- Question 10
- Question 11
- Question 12
- Question 13
- Question 14
- Question 15
- Question 16
- Question 17
- Question 18
- Question 19
- Question 20
- Question 21
- Question 22
- Question 23
- Question 24
- Question 25
Section 3 - Logical Reasoning
- Question 01
- Question 02
- Question 03
- Question 04
- Question 05
- Question 06
- Question 07
- Question 08
- Question 09
- Question 10
- Question 11
- Question 12
- Question 13
- Question 14
- Question 15
- Question 16
- Question 17
- Question 18
- Question 19
- Question 20
- Question 21
- Question 22
- Question 23
- Question 24
- Question 25
Leave a Reply
You must be logged in to post a comment. You can get a free account here.